Started production of the Project at 25th of March, plannig to finish at the beginning of June 2026. Production period continue at workshop.
Started production of the Project at 25th of March, plannig to finish at the beginning of June 2026. Production period continue at workshop.
We started the production of Seawater Reverse Osmosis system ( Desalination System ) for the order we get from Belize, South America. The capacity of the system is 300m3/day. Goods are delivered to Belize at the end of September, goods arrived to Belize at the beginning of November 2025. Customer is building the machine room. After it finished, we will go to in
30m3/day capacity industrial MBBR wastewater treatment plant production for wine factory at Cameroon finished at our workshop, SGS inspeciton test results are waiting for loading.
Goods loaded on 19th of September 2023 as 3 containers. 2x150m3/day capacity MBBR System installation started on 21st of October at Janzour touristic village in Tripoli, Libya
We finished 700x2200 mm Sand Filters and 1100x2200 mm Activated Carbon Filters order for our Hungary Project on 25th of March 2022
SYRIA PROJECT: We started to manufacture 2 pcs, 12 m3/h BWRO System with pre-treatment and feed pump set inside 40 ft Container (refurnished, isolation, air conditioner, with all required piping and cabling inside container) on 3rd of January 2025. Containers delivered to Syria and installed.
We started the Project on 5th of March 2020, we loaded the goods at three party. Last party loaded on 22nd of September 2021.